Capital Two-Year Agency Detail - Eastern Washington State Historical Society
Complete HVAC Controls Replacement
40000052
Funding is provided to complete the modernization and upgrades to HVAC controls. The project will enable all campus facilities to communicate and work with a new control system installed as part of a recent chiller system upgrade and operate more efficiently.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
290,000 | 290,000 |
State Building Construction Account - State | 290,000 |
Garage and Emergency Exit Concrete Remediation
40000053
Water intrusion is causing concrete to spall in the parking garage and adjoining emergency exit. This project will repair the damaged concrete and implement measures to prevent future water infiltration and concrete deterioration.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
901,000 | 901,000 |
State Building Construction Account - State | 901,000 |