Washington State Center for Childhood Deafness and Hearing Loss
Academic and Physical Education Building
30000036
Approved in the 2021-23 biennium, funding is provided for completion of the vision and scope to build the Academic and Physical Education Building. Additional funding was needed for the demolition of Divine High School and Hunter Gym, the construction of a physical education addition onto the new gym to house learning and support spaces, and site improvements including a multi-purpose playfield and city-required frontage improvements, and to address escalation and inflationary cost increases. Reappropriation of unspent prior biennia funding is also included.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
770,000 | 17,173,000 | 37,133,000 | 12,453,000 | 0 | 67,529,000 |
Funds: State Building Construction Account - State | 67,529,000 |
Northrop Primary School Building Renovation
40000006
Renovation of the Northrop Primary School Building is funded. The project includes seismic retrofits; full mechanical, electrical, and plumbing upgrades; and the replacement of the building heating system.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 12,442,000 | 0 | 12,442,000 |
Funds: State Building Construction Account - State | 12,442,000 |
23-25 Minor Works
40000007
Funding is provided for minor capital projects to preserve and extend the life of existing campus facilities and infrastructure systems.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 830,000 | 0 | 830,000 |
Funds: State Building Construction Account - State | 830,000 |