Superintendent of Public Instruction
West Sound Technical Skills Center Modernization
40000015
Funding is provided to construct a new career and technical education facility at the West Sound Technical Skills Center in Bremerton. The new facility's program, design and budget are subject to agency approval.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 332,000 | 11,068,000 | 41,361,000 | 44,343,000 | 97,104,000 |
Funds: State Building Construction Account - State | 97,104,000 |
2023-25 School Construction Assistance Program
40000063
Funds state matching grants to qualifying local school districts for construction, renovation and modernization of K-12 school facilities. Funding may also be made available for study and survey grants to enable districts to qualify for school construction grant assistance.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 616,009,000 | 5,119,823,000 | 5,735,832,000 |
Funds: State Building Construction Account - State | 5,720,832,000 |
Funds: Common School Construction Account - Federal | 15,000,000 |
2023-25 Small District and State Tribal Compact Schools Mod
40000065
This item provides funding for Small District and State Tribal Compact Schools Modernization program to finance all small district modernization grants with revenue generated from the common school trust lands. These grants will allow small and rural school districts that cannot participate in SCAP to access revenue generated by the common school trust lands, regardless of the district’s ability to pass a capital bond or levy. The Small District Modernization Grant Program will fund building system replacement and repairs for districts identified as having significant building system deficiencies and such low property values that replacing or modernizing the school facility through SCAP would present an extraordinary tax burden on property owners or would exceed allowable debt for the district. The grant will also provide additional funding opportunities for tribal compact schools using state general obligation bonds.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 65,098,000 | 446,840,000 | 511,938,000 |
Funds: State Building Construction Account - State | 85,725,000 |
Funds: Common School Construction Account - State | 426,213,000 |
2023-25 School Seismic Safety Grant Program
40000066
Funds state grants to local school districts for seismic retrofit and seismic safety-related improvements of high-risk K-12 school buildings.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 40,000,000 | 160,000,000 | 200,000,000 |
Funds: State Building Construction Account - State | 200,000,000 |
2023-25 School District Health and Safety
40000067
Funding is provided to address school health and safety concerns statewide, prioritizing districts that lack sufficient local funding to address longstanding and urgent facility concerns. This continuing project will provide three grant opportunities to address health and safety, equal access and emergency repairs.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 24,300,000 | 97,200,000 | 121,500,000 |
Funds: State Building Construction Account - State | 121,500,000 |
2023-25 Healthy Kids-Healthy Schools
40000068
Funds competitive grant programs to local school districts to purchase and install water bottle filling stations, improve children's nutrition, increase physical activity and play, and replace water fixtures that test at or above the Environmental Protection Agency action level for lead.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 14,500,000 | 58,000,000 | 72,500,000 |
Funds: Common School Construction Account - State | 72,500,000 |
2023-25 Career Preparation and Launch Capital Grants
40000069
Competitive grants to local school districts to purchase and install equipment that expand Career Connected Learning opportunities are funded.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 6,000,000 | 24,000,000 | 30,000,000 |
Funds: Common School Construction Account - State | 30,000,000 |
2023-25 Skills Centers Minor Works
40000070
Funding is provided for minor capital projects to preserve and extend the useful life of existing Skills Center facilities and supporting infrastructure systems.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 6,817,000 | 27,268,000 | 34,085,000 |
Funds: State Building Construction Account - State | 34,085,000 |
K-12 Capital Programs Administration
40000090
Funding is provided to administer the School Construction Assistance Program and other K- 12 capital grant programs.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 4,839,000 | 0 | 4,839,000 |
Funds: Common School Construction Account - State | 4,839,000 |
Chief Leschi School HVAC
40000099
Funding is provided for a portion of the renovation of the heating, ventilation, and air conditioning (HVAC) system and building controls.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 0 | 0 | 10,000,000 | 0 | 10,000,000 |
Funds: State Building Construction Account - State | 10,000,000 |
Green Schools: Stormwater Infrastructure Projects
91000466
Funds a contract with a statewide, community-based organization with experience planning and developing green stormwater infrastructure and related educational programs on public school properties. The organization must use this funding solely for green stormwater infrastructure projects on public school properties.
Prior Biennium | Current Biennium | Reappropriations | Appropriations | Future Cost | Total Costs |
---|---|---|---|---|---|
0 | 300,000 | 0 | 300,000 | 0 | 600,000 |
Funds: Common School Construction Account - State | 600,000 |