Department of Corrections

WCC: Paint & Repair 300,000 Gallon Water Storage Tank

30000697

Construction funding is provided for lead paint abatement and rust repair for the Washington Corrections Center's 300,000 gallon water tank.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 100,000 400,000 3,006,000 0 3,506,000
Funds: State Building Construction Account - State 3,506,000

LCC: Replace Fire Alarm System

30000772

Funding is provided to replace the obsolete and failing smoke alarm system by upgrading to a system that is code compliant and will protect individuals at the Larch Corrections Center.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 2,456,000 0 2,456,000
Funds: State Building Construction Account - State 2,456,000

SW IMU Recreation Yard Improvement

30001123

Funds the design and construction of larger, more open secure yards at Intensive Management Units throughout the state. The Washington Corrections Center is a priority for 2023-25 funding. Funding is reappropriated to continue remodel of recreation yards from the 2021-23 biennium.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
625,000 111,000 2,264,000 2,000,000 2,000,000 7,000,000
Funds: State Building Construction Account - State 7,000,000

SCCC Roof Replacement

30001128

Design and construction funding is provided to replace 62,500 square feet of the original roofing and failing roof top equipment, including fans or vents.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 6,194,000 0 6,194,000
Funds: State Building Construction Account - State 6,194,000

ECWR: Foundation and Siding

40000067

Funding is provided to repair wood-framed walls and floors on the northeast side of the building and replace the building envelope, which includes siding and windows, at the Eleanor Chase Work Release facility in Spokane.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 100,000 750,000 5,111,000 0 5,961,000
Funds: State Building Construction Account - State 5,961,000

MCC: SOU and TRU - Domestic Water and HVAC Piping System

40000246

Funding is provided for construction to replace the domestic and HVAC water piping and repair wiring and ductwork for HVAC systems at Twin Rivers and Special Offenders Units. A reappropriation of funds is also granted to complete the design.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
106,000 420,000 2,603,000 26,000,000 21,143,000 50,272,000
Funds: State Building Construction Account - State 50,272,000

CBCC: Fire Pump Replacement

40000324

Construction funding is provided to replace the fire suppression water booster pumps and motors required to move large volumes of water when a fire occurs.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 1,411,000 0 1,411,000
Funds: State Building Construction Account - State 1,411,000

Inpatient Psychiatric Unit

40000413

Funding is provided for a predesign to evaluate the best location, alternatives and other analysis needed to design and build an inpatient psychiatric unit to serve the incarcerated population.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 100,000 250,000 2,550,000 17,100,000 20,000,000
Funds: State Building Construction Account - State 20,000,000

CRCC Sage Unit Move to AHCC

40000414

Remaining funding is provided to renovate Airway Heights Corrections Center units to accommodate the special needs, aging and infirm male population that is currently housed at the Coyote Ridge Corrections Center Sage Unit.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 150,000 900,000 1,452,000 0 2,502,000
Funds: State Building Construction Account - State 2,502,000

AHCC: Modular Building for Health Service Staff

40000415

Funding is provided for modular buildings to provide additional space for staffing and medical services at Airway Heights Corrections Center.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 100,000 691,000 408,000 0 1,199,000
Funds: State Building Construction Account - State 1,199,000

CRCC: Modular Building for Health Service Staff

40000416

Funding is provided for modular buildings to provide additional space for staffing and medical services at Coyote Ridge Corrections Center.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 100,000 677,000 428,000 0 1,205,000
Funds: State Building Construction Account - State 1,205,000

McNeil Island Passenger Ferry Replacement

40000418

Funds the design and marine transportation study to evaluate the best alternatives for vessel types and infrastructure required to support a new hybrid passenger ferry.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 900,000 11,158,000 12,058,000
Funds: State Building Construction Account - State 12,058,000

McNeil Island Transport Barge Replacement

40000419

Funding is provided for the design of two new replacement transport barges. The process for ordering and constructing a barge is complicated and lengthy, requiring careful planning and building in extensive lead time for vessel delivery.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 900,000 7,385,000 8,285,000
Funds: State Building Construction Account - State 8,285,000

Minor Works Preservation Projects

40000427

Minor works preservation funding is provided to reduce risks to people and property and maximize the function and utility of state assets.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
0 0 0 11,417,000 61,689,000 73,106,000
Funds: State Building Construction Account - State 73,106,000

WSP: Unit Six Roof Replacement

92000037

Funding is provided to construct a new roof and roof-top heating ventilation and air conditioning equipment on Unit 6 at the Washington State Penitentiary. A reappropriation is also granted to complete design of the project.

Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Costs
639,000 412,000 374,000 12,569,000 0 13,994,000
Funds: State Building Construction Account - State 13,994,000