Eighteenth Legislative District

Project ID
Project Title
Estimate Total Prior Expenditures Reapprop. 2021-23 New Approp. 2021-23 Estimated New Approp. 2023-25 Estimated New Approp. 2025-27 Estimated New Approp. 2027-29 Estimated New Approp. 2029-31

300 Department of Social and Health Services

40000536
Special Commitment Center-Clark County CSTF: New Construction
8,185,000 8,185,000

310 Department of Corrections

30000754
LCC Pave North Access Road
2,728,000 200,000 2,528,000
40000089
LCC: Parking Lot Erosion Control
2,222,000 222,000 2,000,000
40000255
LCC: Boiler Replacement
4,995,000 1,300,000 3,695,000
40000275
LCC: Control Room Sally Port
2,200,000 200,000 2,000,000
Total for Department of Corrections 12,145,000 1,300,000 3,695,000 200,000 2,422,000 4,528,000

465 State Parks and Recreation Commission

30000687
Seaquest - Replace Day Use Comfort Station
642,000 642,000
40000237
Battle Ground Lake Pave Roads and Parking Lots
950,000 950,000
40000238
Battle Ground Lake Replace Playgound Equipment
250,000 250,000
40000256
Battle Ground Lake Replace Residence
400,000 400,000
40000257
Battle Ground Lake Replace Welcome Center
450,000 450,000
Total for State Parks and Recreation Commission 2,692,000 1,492,000 1,200,000

699 Community and Technical College System

30000135
Clark College: North County Satellite
58,918,000 401,000 5,287,000 53,230,000
Total for Eighteenth Legislative District 81,940,000 401,000 5,287,000 54,530,000 5,187,000 8,385,000 2,422,000 5,728,000