Project ID Project Title |
Estimate Total | Prior Expenditures | Reapprop. 2021-23 | New Approp. 2021-23 | Estimated New Approp. 2023-25 | Estimated New Approp. 2025-27 | Estimated New Approp. 2027-29 | Estimated New Approp. 2029-31 |
---|---|---|---|---|---|---|---|---|
300 Department of Social and Health Services |
||||||||
40000536 Special Commitment Center-Clark County CSTF: New Construction |
8,185,000 | 8,185,000 | ||||||
310 Department of Corrections |
||||||||
30000754 LCC Pave North Access Road |
2,728,000 | 200,000 | 2,528,000 | |||||
40000089 LCC: Parking Lot Erosion Control |
2,222,000 | 222,000 | 2,000,000 | |||||
40000255 LCC: Boiler Replacement |
4,995,000 | 1,300,000 | 3,695,000 | |||||
40000275 LCC: Control Room Sally Port |
2,200,000 | 200,000 | 2,000,000 | |||||
Total for Department of Corrections | 12,145,000 | 1,300,000 | 3,695,000 | 200,000 | 2,422,000 | 4,528,000 | ||
465 State Parks and Recreation Commission |
||||||||
30000687 Seaquest - Replace Day Use Comfort Station |
642,000 | 642,000 | ||||||
40000237 Battle Ground Lake Pave Roads and Parking Lots |
950,000 | 950,000 | ||||||
40000238 Battle Ground Lake Replace Playgound Equipment |
250,000 | 250,000 | ||||||
40000256 Battle Ground Lake Replace Residence |
400,000 | 400,000 | ||||||
40000257 Battle Ground Lake Replace Welcome Center |
450,000 | 450,000 | ||||||
Total for State Parks and Recreation Commission | 2,692,000 | 1,492,000 | 1,200,000 | |||||
699 Community and Technical College System |
||||||||
30000135 Clark College: North County Satellite |
58,918,000 | 401,000 | 5,287,000 | 53,230,000 | ||||
Total for Eighteenth Legislative District | 81,940,000 | 401,000 | 5,287,000 | 54,530,000 | 5,187,000 | 8,385,000 | 2,422,000 | 5,728,000 |