Ninth Legislative District
Project ID Project Title |
Estimate Total | Prior Expenditures | Reapprop. 2021-23 | New Approp. 2021-23 | Estimated New Approp. 2023-25 | Estimated New Approp. 2025-27 | Estimated New Approp. 2027-29 | Estimated New Approp. 2029-31 |
---|---|---|---|---|---|---|---|---|
303 Department of Health |
||||||||
40000008 Othello Water Supply and Storage |
1,550,000 | 700,000 | 850,000 | |||||
310 Department of Corrections |
||||||||
30001124 CRCC Security Electronics Network Renovation |
6,000,000 | 2,000,000 | 4,000,000 | |||||
365 Washington State University |
||||||||
30001322 Global Animal Health Building |
59,400,000 | 57,527,000 | 1,873,000 | |||||
30001326 Washington State University Pullman - STEM Teaching Labs |
9,900,000 | 4,900,000 | 5,000,000 | |||||
30001326 Washington State University Pullman - STEM Teaching Labs |
1,000,000 | 1,000,000 | ||||||
40000013 Information Technology Renovations |
10,000,000 | 5,000,000 | 5,000,000 | |||||
40000271 Johnson Hall Replacement |
8,000,000 | 8,000,000 | ||||||
40000272 Campus Fire Protection and Domestic Water Reservoir |
8,000,000 | 8,000,000 | ||||||
40000273 STEM Teaching and Replacement Building - VCEA |
53,000,000 | 8,000,000 | 45,000,000 | |||||
40000274 Clark Hall Research Lab Renovation |
4,900,000 | 4,900,000 | ||||||
40000277 Learning Renovations |
20,000,000 | 10,000,000 | 10,000,000 | |||||
40000278 Research Renovations |
10,000,000 | 10,000,000 | ||||||
40000280 Building Systems (roofs, elevators, envelope, BAS, MEP) |
20,000,000 | 10,000,000 | 10,000,000 | |||||
40000281 Bustad Renovation (Replacement for Vet Teaching Anatomy) |
10,000,000 | 10,000,000 | ||||||
40000282 McCoy Hall Demolition |
8,000,000 | 8,000,000 | ||||||
40000283 Murrow Hall Renovation |
3,000,000 | 3,000,000 | ||||||
40000284 Pullman Sciences Building |
53,500,000 | 500,000 | 53,000,000 | |||||
40000285 Fulmer Hall Renovation Ph 1 |
38,000,000 | 3,000,000 | 35,000,000 | |||||
40000287 Engineering Renovation/Replacement Ph 2 - VCEA |
8,000,000 | 8,000,000 | ||||||
Total for Washington State University | 324,700,000 | 58,527,000 | 1,873,000 | 26,300,000 | 53,000,000 | 48,000,000 | 58,000,000 | 79,000,000 |
465 State Parks and Recreation Commission |
||||||||
30000327 Camp Wooten Bunkhouse with ADA |
320,000 | 320,000 | ||||||
30000342 Fields Spring Restroom ADA Upgrades |
465,000 | 465,000 | ||||||
30000343 Field Spring Electrical Upgrade |
348,000 | 348,000 | ||||||
30000754 Potholes Construct Storage Building |
237,000 | 237,000 | ||||||
30000951 Field Spring Replace Failed Sewage Syst & Non-ADA Comfort Station |
1,268,000 | 294,000 | 974,000 | |||||
30000983 Palouse Falls Day Use Area Renovation |
2,995,000 | 1,000 | 219,000 | 2,775,000 | ||||
30001076 Steptoe Butte Road Improvements |
466,000 | 466,000 | ||||||
40000233 Steptoe Butte Heritage Site Interpretation |
200,000 | 200,000 | ||||||
40000324 Fields Spring Entrance Road Paving Including Admin Area |
120,000 | 120,000 | ||||||
40000332 Lyons Ferry Shoreline Bulkhead Renovation |
250,000 | 250,000 | ||||||
40000334 Palouse to Cascades Trail Erosion at Ponderosa/Turkey Gulch |
50,000 | 50,000 | ||||||
40000336 Palouse to Cascades Trail Lind to Malden Trail Improvements |
1,000,000 | 1,000,000 | ||||||
40000337 Palouse to Cascades Trail Rosalia Trailhead |
600,000 | 600,000 | ||||||
40000339 Potholes Day Use Renovation |
1,600,000 | 1,600,000 | ||||||
40000340 Potholes Shop and Contact Station Improvements |
750,000 | 750,000 | ||||||
40000357 Columbia Plateau Trail Snake River Junction to Kahlotus Trailhead |
464,000 | 464,000 | ||||||
Total for State Parks and Recreation Commission | 11,133,000 | 761,000 | 1,193,000 | 2,775,000 | 4,020,000 | 584,000 | 1,800,000 | |
Total for Ninth Legislative District | 343,383,000 | 61,988,000 | 7,916,000 | 29,075,000 | 57,020,000 | 48,584,000 | 59,800,000 | 79,000,000 |