Washington State Center for Childhood Deafness and Hearing Loss
Major Function, Agency, Project | Estimate Total | Prior Expenditures | Reapprop. 2021-23 | New Approp. 2021-23 | Estimated New Approp. 2023-25 | Estimated New Approp. 2025-27 | Estimated New Approp. 2027-29 | Estimated New Approp. 2029-31 |
---|---|---|---|---|---|---|---|---|
30000036 Academic and Physical Education BuildingState Building Construction Account - State |
50,012,000 | 2,707,000 | 2,930,000 | 44,375,000 | ||||
30000045 Minor Works: Preservation 2019-21State Building Construction Account - State |
500,000 | 500,000 | ||||||
30000047 Minor Works: Preservation 2021-23State Building Construction Account - State |
500,000 | 500,000 | ||||||
Washington State Center for Childhood Deafness and Hearing Loss Fund Summary |
||||||||
State Building Construction Account - State | 51,012,000 | 3,207,000 | 2,930,000 | 44,875,000 | ||||
Total for Washington State Center for Childhood Deafness and Hearing Loss | 51,012,000 | 3,207,000 | 2,930,000 | 44,875,000 |