Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000002 - Creative Districts Capital Construction
C00 057 Y N 368,390 368,390 18,750 89,028 89,028 24% 24% 279,362
30000003 - 2023-25 Creative Districts Capital Projects Program
D00 057 N N 416,000 53,638 118,636 512 6,964 6,964 2% 2% 111,672
30000004 - Preserving State-owned Public Art
D01 057 N N 735,000
387 - Washington State Arts Commission Totals 1,519,390 53,638 487,026 19,262 95,992 26% 26% 391,034%