380 - Western Washington University

Last Updated: 10/07/2024

Through September 2024

Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000604 - Access Control Security Upgrades
C00 057 Y N 770,560 770,560 581,572 (1,200) 580,372 75% 75% 188,988
C01 065 Y N 554,480 554,480 55,488 387,164 (55,488) 331,676 60% 70% 167,316
D00 057 N N 6,250,000 498,333 1,266,666 39,000 39,000 0.62% 1,266,666
Totals 7,575,040 498,333 2,591,706 55,488 968,736 (17,688) 951,048 136% 145% 1,622,970%
30000872 - Electrical Engineering/Computer Science
C02 057 Y N 39,281,060 2,000,000 38,040,535 7,470 38,982,132 (7,470) 38,974,662 99% 99% (941,597)
C10 065 Y N 1,500,000 1,500,000 42,306 42,306 3% 3% 1,457,694
C12 26V Y N 1,863,000 450,000 1,500,000 1,863,000 1,863,000 100% 100% (363,000)
Totals 42,644,060 2,450,000 41,040,535 7,470 41,856,174 (7,470) 40,879,968 202% 202% 153,097%
30000911 - 2021-23 Classroom & Lab Upgrades
C03 057 Y N 1,393,280 1,393,280 2,327 697,670 167,669 865,339 62% 50% 695,610
30000912 - Coast Salish Longhouse
C04 057 Y N 2,627,030 113,940 1,487,619 223,652 656,059 1,841,214 2,497,273 95% 25% 831,560
C05 065 Y N 1,500,000 100,000 500,000 95,278 95,278 1,183,517 1,278,795 85% 6% 404,722
Totals 4,127,030 213,940 1,987,619 318,930 43,305,181 3,024,731 3,776,068 180% 31% 1,236,282%
30000915 - Minor Works - Preservation 2021-23
C06 065 Y N 2,067,740 2,067,740 19,838 1,951,739 1,951,739 94% 94% 116,001
30000918 - Minor Works - Program 2021-2023
C07 065 Y N 277,720 277,720 6,882 37,886 37,886 14% 14% 239,834
C11 057 Y N 404,460 404,460 327,318 327,318 81% 81% 77,142
Totals 682,180 682,180 6,882 45,622,124 365,204 95% 95% 316,976%
30000919 - Student Development and Success Center
D01 057 N N 47,950,000 1,250,000 3,235,000 736,530 3,415,592 4,152,122 9% 2% 2,498,470
40000004 - Environmental Studies Renovation
D02 057 N N 500,000 500,000 491,143 491,143 98% 98% 8,857
40000005 - Heating Conversion Project
D03 26C N N 10,000,000 476,190 5,238,090 12,553 733,174 36,777 769,951 8% 7% 4,504,916
40000006 - Minor Works - Preservation 2023-25
D04 065 N N 5,388,000 212,522 2,762,786 7,178 730,366 87,670 818,036 15% 14% 2,032,420
40000007 - Minor Works - Program 2023-25
D05 065 N N 3,000,000 130,435 1,695,655 159,172 843,151 (137,210) 705,941 24% 28% 852,504
40000008 - Classroom, Lab, and Collaborative Space Upgrades
D06 057 N N 1,500,000 65,217 847,821 9,242 94,464 85,077 179,541 12% 6% 753,357
40000012 - Preventative Facility Maintenance and Building System Repairs
D07 065 N N 3,614,000 150,583 2,108,166 162,546 2,134,718 2,134,718 59% 59% (26,552)
380 - Western Washington University Totals 130,441,330 5,447,220 66,150,578 761,626 6,655,148 58,040,818 993% 832% 14,764,908%