Auth Code Fund Reapprop Provisos Current Biennium Appropriation Budgeted Cost of Work (Allotted) Actual Cost of Work Outstanding Contracting Balance (Encumbered) Total Dollars Obligated Percent Obligated Percent Expended Biennium to Date Variance (Allotted - Actuals)
This Month Biennium to Date This Month Biennium to Date
30000035 - Minor Works Preservation Projects
D00 608 N N 999,000
D01 609 N N 997,000
Totals 1,996,000
30000043 - Modernize Lab and Training Facility
A06 608 Y N 2,113,580 2,113,580 164,630 1,030,924 1,030,924 49% 49% 1,082,656
A07 609 Y N 362,860 362,860 28,916 181,774 181,774 50% 50% 181,086
Totals 2,476,440 2,476,440 193,546 1,212,698 1,212,698 99% 99% 1,263,742%
30000059 - Air Handler Retrofit and Cooling Tower R
C02 608 Y N 222,760 222,760 222,760
C03 609 Y N 222,760 222,760 222,760
Totals 445,520 445,520 1,212,698 445,520%
40000014 - Interior Lighting and Controls Upgrade
D02 26C N N 1,925,000 30,000 30,000
40000015 - Solar Panel Installation - Lab & Training Facility
D03 26C N N 3,734,000 2,232,464 18,515 1,711,793 1,711,793 46% 46% 520,671
235 - Department of Labor and Industries Totals 10,576,960 5,184,424 212,061 2,924,491 145% 145% 2,259,933%